Real build · SIP 950
A real SIP 950, from the truck to the roof.
A customer’s SIP 950, photographed from the morning the trucks arrived to the day the roof panels went on. About three weeks, start to shell.
July 20
Delivery day
July 20–22
Foundation and floor deck
July 27–30
Walls and gables
August 7
Roof panels
August 11
Shell standing, roof on
Delivery day
The kit arrived on two flatbeds the morning of July 20. The panels came off with the truck’s crane and a telehandler and were staged beside the foundation, ready to raise.
Plan for the same on your site: a road the truck can reach, a level spot to stage the load, offload equipment and a few hands. Each truck gives you a two-hour offload window.
Delivery terms in the FAQ




The build

01 · July 20
Foundation

02 · July 21
Floor framing

03 · July 22
Floor deck

04 · July 27
Walls go up

05 · July 29
Gables

06 · August 7
Roof panels

07 · August 7
Roof set

08 · August 11
Shell standing
The whole build in 90 seconds
A time-lapse of the same house, from the bare deck to the roof.
The windows went on backorder with the manufacturer, so finishing is waiting on them. We’ll add photos of the finished house when it’s done.